Home > Historic Buildings > Brabyns Hall > Iron Bridge Restoration
Can your business or organisation help support this site too?

118_1865b.jpg
2008-05-16 Wing Walls and RailsIt's a long time since the railings on the iron bridge have looked this good.
118_1859b.jpg
2008-05-16 Wright's LogoBoth of the handrail centre pieces with Nathaniel Wright's logo at the apex of the bridge have been repaired and reinstalled.
118_1874a.jpg
2008-05-23 Concrete DeckAbutments repointed and railings repaired.
118_1869a.jpg
2008-05-23 Concrete DeckThe concrete infill is applied to the new steel deck. The box-outs are inspection pits for the bearings.
118_1873a.jpg
2008-05-23 Concrete DeckThe underside of the steel deck after grouting between the cast iron bridge and the hollow box section beams.
118_1875a.jpg
2008-05-23 Concrete DeckA trowelled finish is applied to the concrete infill.
118_1876a.jpg
2008-05-23 Concrete DeckLevelling up the approach to the bridge on the Rollins Lane side.
118_1877a.jpg
2008-05-23 Concrete DeckA wide angle view of the approach on the park side during application of the concrete infill over the steel deck.
leaf_framed.jpg
2008-05-29 a Leafy ViewA leafy view of the bridge before scaffold removal begins. Photo Aidan / Oly.
Concete_Deck.jpg
2008-05-29 Concrete DeckingThe concrete decking has now cured. Photo Aidan / Oly.
circles.jpg
2008-05-29 Under the BridgeLast close up views of the rings from under the bridge before the scaffold removal begins. Photo Aidan / Oly.
more_circles.jpg
2008-05-29 Under the BridgeLast close up views of the rings from under the bridge before the scaffold removal begins. Photo Aidan / Oly.
299 files on 25 page(s) 18